Update on work schedule

Work is still on schedule.  The paths are now just about complete.  Work has stopped on the first cabin as our high tech composting toilets are caught up in a strike in Sweden.  Once we get them the en-suite will be installed, the cabin painted and all the furnishings installed to allow us to show you pictures of the first completed cabin (Red Squirrel).  Meanwhile, windows are being prepared, logs are being stripped to support the covered roof areas, the rustic headboards are cut ready to be installed, bedding ordered, colour schemes being decided outdoor stoves and baths being designed, mattress testing to make sure they are comfortable and other design decisions being deliberated over.  It’s all go!